  • Permit: #COM-1913192
    Cannabis Extraction Lab (Commercial Remodel)

    Verify Wait
    Description:
    EPC Submittal - Remodel of Commercial Building - Warehouse remodeled to new Cannabis Extraction Lab. New interior partition walls, installation of new engineered booth enclosures, new ADA restrooms and plumbing fixtures, new mechanical systems, new electric systems, restripe existing parking lot - PLNG-INSP
    Last Updated: Jan 8, 2020

    Review

    Review Begin
    Cycle 5 Begin

    History:
    Jul 16, 2019
    Cycle 1 Begin
    Sep 11, 2019
    Cycle 2 Begin
    Oct 14, 2019
    Cycle 3 Begin
    Nov 18, 2019
    Cycle 4 Begin
    Dec 21, 2019
    Cycle 5 Begin
    Last Updated: 2020-01-04 05:02:52 UTC
    Development Engineering Review
    Verify Cycle 1 Approved

    History:
    Jul 19, 2019
    Cycle 1 Correction
    Sep 11, 2019
    Cycle 2 Approved
    Jan 2, 2020
    Verify Cycle 1 Approved

    Plan Review Comments

    Jul 19, 2019
    Please refer to comment letter

    Sep 11, 2019
    Based on the limited documents provided for review, the Public Works Department has not identified any conflict between the plans for the structure/improvements and other existing property interest.

    Jan 2, 2020
    Based on the limited documents provided for review, the Public Works Department has not identified any conflict between the plans for the structure/improvements and other existing property interest.
    Last Updated: 2020-01-04 05:02:54 UTC
    Utilities Review
    Verify Cycle 1 Approved

    History:
    Jul 29, 2019
    Cycle 1 Correction
    Sep 23, 2019
    Cycle 2 Correction
    Oct 15, 2019
    Cycle 3 Approved
    Jan 2, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-04 05:02:54 UTC
    Plumbing
    Verify Cycle 1 Approved

    History:
    Aug 6, 2019
    Cycle 1 Correction
    Sep 24, 2019
    Cycle 2 Correction
    Oct 25, 2019
    Cycle 3 Correction
    Nov 26, 2019
    Cycle 4 Correction
    Dec 23, 2019
    Cycle 5 Approved
    Jan 2, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-04 05:02:53 UTC
    Mechanical Review
    Verify Cycle 1 Approved

    History:
    Aug 6, 2019
    Cycle 1 Correction
    Sep 24, 2019
    Cycle 2 Correction
    Oct 25, 2019
    Cycle 3 Correction
    Nov 26, 2019
    Cycle 4 Correction
    Dec 23, 2019
    Cycle 5 Approved
    Jan 2, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-04 05:02:53 UTC
    Planning Review
    Verify Cycle 1 Approved

    History:
    Aug 6, 2019
    Cycle 1 Approved
    Jan 2, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-04 05:02:55 UTC
    Fire Review
    Verify Cycle 1 Approved

    History:
    Jul 26, 2019
    Cycle 1 Correction
    Sep 18, 2019
    Cycle 2 Approved
    Oct 23, 2019
    Cycle 3 Approved
    Oct 24, 2019
    Cycle 3 Correction
    Nov 17, 2019
    Cycle 3 Approved
    Dec 23, 2019
    Cycle 5 Approved
    Jan 6, 2020
    Verify Cycle 1 Approved

    Plan Review Comments

    Sep 18, 2019
    approved - WITH CONDITIONS

    Oct 23, 2019
    approved with conditions

    Nov 17, 2019
    approved with conditions - only condition being that this was reviewed as an AMMR submittal

    Dec 23, 2019
    approved - see notes
    Last Updated: 2020-01-07 05:03:13 UTC
    Electrical Review
    Verify Cycle 1 Approved

    History:
    Aug 6, 2019
    Cycle 1 Correction
    Sep 26, 2019
    Cycle 2 Correction
    Oct 18, 2019
    Cycle 3 Correction
    Nov 25, 2019
    Cycle 4 Approved
    Jan 6, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-07 05:03:12 UTC
    Structural Review
    Verify Cycle 1 Approved

    History:
    Aug 8, 2019
    Cycle 1 Correction
    Sep 20, 2019
    Cycle 2 Correction
    Oct 21, 2019
    Cycle 3 Approved
    Jan 6, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-07 05:03:12 UTC
    Life Safety Review
    Verify Cycle 1 Approved

    History:
    Aug 8, 2019
    Cycle 1 Correction
    Sep 20, 2019
    Cycle 2 Correction
    Sep 27, 2019
    Cycle 2 Correction
    Oct 21, 2019
    Cycle 3 Approved
    Jan 6, 2020
    Verify Cycle 1 Approved
    Last Updated: 2020-01-07 05:03:12 UTC
    Formal Review
    Approved

    Plan Review Comments

    Jan 6, 2020
    Formal Review Subtasks Complete - Script7
    Last Updated: 2020-01-07 05:03:11 UTC
    Air Quality Review
    Application Expired

    History:
    Aug 14, 2019
    Cycle 1 Correction
    Oct 1, 2019
    Cycle 2 Correction
    Oct 28, 2019
    Cycle 3 Correction
    Dec 5, 2019
    Cycle 4 Correction
    Jan 2, 2020
    Cycle 5 Approved
    Jul 1, 2020
    Application Expired

    Plan Review Comments

    Aug 14, 2019
    Your cannabis business may include processes jurisdictional to District Rule 201 – General Permitting.

    Please contact Victoria Pena [916] 874-4848 Vpena@airquality.org or Jeffrey Yang [916] 874-4550 Jyang@airquality.org for assistance.

    For more information: http://www.airquality.org/businesses/permits-registration-programs/permit-applications-recordkeeping-advisories/cannabis-operations

    Oct 1, 2019
    Your cannabis business may include processes jurisdictional to District Rule 201 – General Permitting.

    Please contact Victoria Pena [916] 874-4848 Vpena@airquality.org or Jeffrey Yang [916] 874-4550 Jyang@airquality.org for assistance.

    For more information: http://www.airquality.org/businesses/permits-registration-programs/permit-applications-recordkeeping-advisories/cannabis-operations



    This project is jurisdictional to SMAQMD Rule 902 - Asbestos. Please conduct an asbestos survey and complete a District renovation/demolition notification form; Please submit both documents to Asbestos@airquality.org

    For more information please contact Jeffrey Yang (916)874-4550 or visit http://www.airquality.org/Businesses/Asbestos/Asbestos-in-Building-Materials

    Oct 28, 2019
    Your cannabis business may include processes jurisdictional to District Rule 201 – General Permitting.

    Please contact Victoria Pena [916] 874-4848 Vpena@airquality.org or Jeffrey Yang [916] 874-4550 Jyang@airquality.org for assistance.

    For more information: http://www.airquality.org/businesses/permits-registration-programs/permit-applications-recordkeeping-advisories/cannabis-operations



    This project is jurisdictional to SMAQMD Rule 902 - Asbestos. Please conduct an asbestos survey and complete a District renovation/demolition notification form; Please submit both documents to Asbestos@airquality.org

    For more information please contact Jeffrey Yang (916)874-4550 or visit http://www.airquality.org/Businesses/Asbestos/Asbestos-in-Building-Materials

    Dec 5, 2019
    Your cannabis business may include processes jurisdictional to District Rule 201 – General Permitting.

    Please contact Victoria Pena [916] 874-4848 Vpena@airquality.org or Jeffrey Yang [916] 874-4550 Jyang@airquality.org for assistance.

    For more information: http://www.airquality.org/businesses/permits-registration-programs/permit-applications-recordkeeping-advisories/cannabis-operations



    This project is jurisdictional to SMAQMD Rule 902 - Asbestos. Please conduct an asbestos survey and complete a District renovation/demolition notification form; Please submit both documents to Asbestos@airquality.org

    For more information please contact Jeffrey Yang (916)874-4550 or visit http://www.airquality.org/Businesses/Asbestos/Asbestos-in-Building-Materials

    Jan 2, 2020
    Please be aware that your cannabis business may include processes jurisdictional to District Rule 201 – General Permitting. You must contact air quality permitting staff prior to installing any equipment or activating any process lines that may require a permit to operate.

    Please contact Victoria Pena (916)874-4848 or vpena@airquality.org or Jeffrey Yang (916) 874-4550 or jyang@airquality.org for assistance.

    For more information, please visit: http://www.airquality.org/businesses/permits-registration-programs/permit-applications-recordkeeping-advisories/cannabis-operations





    Based on your statement, Sacramento Metropolitan Air Quality Management District (Sac Metro Air District) Rule 902, Asbestos is not applicable to your renovation project. District notification is not needed unless the scope of work changes to include demolition of structural/load-bearing elements or renovation of greater than 160sqft of materials.

    For more information please contact Daniel Noakes (916)874-7493 or visit http://www.airquality.org/Businesses/Asbestos/Asbestos-in-Building-Materials

    Jul 1, 2020
    Task completed by batch script BuildingApplicationExpiration
    Last Updated: 2020-08-11 23:12:36 UTC
    Air Quality Review
    Target Date: Jan 6, 2020
    to receive an email alert when the next activity occurs
  • Permit: #SUB-1912652
    Commercial Plan Review Submittal

    Accepted
    Description:
    EPC Submittal - Remodel of Commercial Building - New interior partition walls, installation of new engineered booth enclosures, new ADA restrooms and plumbing fixtures, new mechanical systems, new electric systems, restripe existing parking lot
    Last Updated: Jul 8, 2019
    to receive an email alert when the next activity occurs
  • Permit: #COM-1912551
    7941 Butte Ave - Remodel Estimate (Commercial Remodel)

    Estimate
    Description:
    Remodel to include: New interior partition walls, installation of new booth enclosures. New accessible restroom and plumbing fixtures, new mechanical systems, new electrical systems.
    Last Updated: Jul 8, 2019
    to receive an email alert when the next activity occurs
  • Plan: #Z17-228
    New Wave Gardens CUP (Z Files)

    Withdrawn
    Description:
    A request for a Conditional Use Permit for cannabis cultivation within an existing warehouse on a 0.11-acres parcel in the Light Industrial, Solid Waste Restricted (M-1-SWR) zone, within the Sacramento Center for Innnovation (SCI) Specific Plan.

    Contact:
    Miriam Lim
    916-808-3540
    Last Updated: Dec 14, 2017
    Application Submittal
    Ready for Review

    Comments

    Dec 8, 2017
    Delivered to Zoning Administrator inbox.
    Last Updated: 2017-12-12 05:25:12 UTC
    Zoning Review
    Withdrawn

    Plan Review Comments

    Dec 26, 2017
    Project withdrawn by applicant. Fees to be refunded.
    Last Updated: 2017-12-27 05:13:54 UTC
    to receive an email alert when the next activity occurs
  • Permit: #COM-1509709
    Commercial Minor

    Finaled
    Description:
    REMOVAL OF ELECTRICAL, PER APPLICANT, IT WAS IDENTIFIED BY SMUD, AS HAVING BEEN INSTALLED WITHOUT PERMITS AND REQ. REMOVAL AND VERIFICATION OF REMOVAL BY INSPECTION.
    Last Updated: Jul 21, 2015

    Inspection

    79 Elect FINAL
    Approved

    Inspector's Comments

    Jul 22, 2015
    Last Updated: 2015-07-22 11:54:31 UTC
    to receive an email alert when the next activity occurs
  • Permit: #COM-1410678
    Commercial Minor

    Finaled
    Description:
    CHANGING TO 200AMP SERVIVE PER SMUD REQUEST.
    Last Updated: Aug 28, 2014
    Tech Review
    Ready-to-Issue

    Inspection

    79 Elect FINAL
    Approved

    Inspector's Comments

    Aug 29, 2014
    2014-08-29
    Kim L Hagen
    ATTACHED AND E-MAILED
    Last Updated: 2014-10-23 02:00:51 UTC
    to receive an email alert when the next activity occurs
  • Permit: #COM-1407684
    Commercial Revision

    Complete
    Description:
    EXPEDITED - REVISION OTC TO COM-1403942 CHANGE SERVICE PANEL 100AMP TO 200AMP
    Last Updated: Jun 25, 2014
    Tech Review
    Approved Over the Counter

    Permit Issuance

    Processing Permit
    Ready For Pickup
    Ready For Pickup
    Complete
    to receive an email alert when the next activity occurs
  • Permit: #COM-1403942
    Commercial Repair-Maintenance

    Finaled
    Description:
    EXPEDITED - CHANGING FROM 100 AMP SERVICE TO 400 AMP (OTC)
    Last Updated: Apr 7, 2014
    Tech Review
    Approved Over the Counter

    Permit Issuance

    Processing Permit
    Ready-to-Issue
    Ready To Issue
    Permit Issued; applicant can begin work
    Issued
    Finaled

    Inspection

    67 Elect-Temp Power-SMUD
    Approved

    Inspector's Comments

    Jun 26, 2014
    2014-06-26
    Kim L Hagen
    E-mail and attached
    Last Updated: 2014-10-22 21:03:50 UTC
    79 Elect FINAL
    Approved

    History:
    Apr 22, 2014
    Correction Notice
    Jun 24, 2014
    Cancelled
    Jun 26, 2014
    Cancelled
    Jul 11, 2014
    Approved

    Inspector's Comments

    Apr 22, 2014
    2014-04-22
    Kim L Hagen
    1. Support UFER with non-metalic stakes maximum 36" appart.

    2. Provide new 100 amp panel with top buss connection for breaker not over 6'7" above floor.

    3. Provide connectors for cable connection to metal boxes.

    4. Remove equipment not intended for continued use.

    5. Close unused openings of boxes.

    6. seal open spaces of breakers removed.

    7. Provide point of attachment for service drop at minimum 16' above private driveway.

    Jun 24, 2014
    2014-06-24
    Kim L Hagen
    by phone, contractor at the counter.
    Last Updated: 2014-10-22 21:03:49 UTC
    to receive an email alert when the next activity occurs